Project Costs and Financing

Project Costs and Financing

The project budget was as follows:

  

Description

 

Land Acquisition Costs (Former Gas Station & Retail Store & MNR/ORC acquisition)

$850,000

Demolition of Retail Store, Gas Station, UGT Removal, Town Hall

$145,000

Removal of Impacted Soils

$200,000

Environmental Consultant

$60,000

Placement of Engineered Fill

$200,000

Design Services (Architects & Engineers)

$540,000

Proposed Building:

Basement

First and Second Floor

 

7,226 sq ft

19,225 sq ft

Estimated Cost Per Square Foot (LEED Silver)
Basement

First and Second Floor

 

$130/sq ft

$240/sq ft

Total Estimated Construction Cost

$5.6 million

External Parking Lot Development

$85,000

Furniture, Fixtures & Equipment

$250,000

Site Works, Landscaping

$300,000

Moving

$50,000

Contingency @ 3.5%

$168,000

TOTAL

$8,448,000

Change orders were within budget. Below is a summary of those items:

Item Description                                               

Budget Amount ($)                   Awarded Bid ($) (GST/HST Extra)
Piling 500,00 468,500
Foundations/Structural Slabs 624,373 272,220
Structural Steel 439,500 308,000
Reinforcing Steel 84,600 83,916
Precast Slabs 71,670 47,975
Concrete Decks and Topping 41,751 23,045
Elevator 90,000 59,368
Wood Decking 59,800 49,933
Mechanical 890,655 1,040,800
Electrical 325,710 723,124
Sprinklers 74,118 57,680
Steel Studs/Drywall/Insulation 279,125 347,000
Brick,Stone and Concrete Block Masonry 334,410 432,022
Aluminum Windows and Curtainwall 463,400 510,500
Metal Doors and Frames 5,400 6,210
Steel Handrail and Miscellaneous Metals 60,400 43,360

Flat Roof

178,710

77,458

Metal Roof

81,240

57,307

Rough Carpentry

30,000

67,970

Waterproofing

9,160

11,500

Site Development

15,250

15,250

Site Works (excavation,grading,etc.)

116,750

100,000

Credits

n/a

(25,680)

Change Orders

n/a

45,817

Contingency

168,000

n/a

Total

4,944,022

4,822,275

In 2009, a grant of $4.6 million was received by the Town of The Blue Mountains, through the Infrastructure Stimulus Fund (ISF).  This grant will offset the total cost of the project.  Therefore the cost of the project for the municipality is approximately $3,848,000. 

The Town has recently received confirmation from the Federation of Canadian Municipalities  Green Municipal Fund that our Energy Application was successful. The Grant commitment is $330,000 and the Loan commitment is $3.3 million (with the same being at 1.5% below the Bank of Canada Bond Rate).  Upon the building being complete, and it is demonstrated by the Town that the building has achieved the energy efficiency results contained in our application, the Loan and Grant will become available.

The Town has also submitted a 'High Performance New Construction Program' application related to expected modelled energy savings. This program provides for incentives based on the expected energy savings.  In the Town's instance, the incentive applied for is $9.900.         

For more information regarding expected Capital Resource Requirements and Sources of Financing and Funding, please contact Darcy Chapman, Capital Accountant, Town of The Blue Mountains, at dchapman@thebluemountains.ca.

 