Construction completed in Pressure Zone 4C

Tyrolean Village Water Distribution Improvements

On this page:
1. Project Updates
2. Public Meetings & Information Centres 

In 2015/2016 the Town completed a review and update of the calibrated hydraulic water model which included a needs assessment analysis of the Town’s water distribution system. The review identified existing deficiencies within the boundary of Pressure Zone 4C, also known as Tyrolean Village, and provided recommendations for infrastructure upgrades in the area.

The preferred solution identified through the preliminary design includes:

  • the removal of the existing pressure relief valve, and the addition of two new pressure relief valves
  • extension of the existing watermain on Craigmore Crescent to loop the existing watermain to Settler’s Way (approx. 80m)
  • the installation of approximately 70m of new watermain on Birch View Trail from Arlberg Crescent to Brooker Boulevard

The project will include restoration only in areas disturbed by the installation of the necessary infrastructure. Full road reconstruction is not being considered as part of this project.

Why Now?

The Town is completing this project to address existing deficiencies, and to improve water pressure and fire flow within the area.


Project Updates

August 12, 2022

Arnott Construction Limited will be re-mobilizing the week of August 15, 2022 to correct deficiencies found in the Tyrolean Village (Pressure Zone 4C) Water Distribution Improvement Project. Work will be completed in the areas of Craigmore Crescent, Tyrolean Lane, Arlberg Crescent, Birch View Trail and Settlers Way. These works will include repairs to:

  • Boulevards and ditches
  • Culverts
  • Fire hydrant ramps
  • Underground water chambers

The impacts of this work will include construction noise, possibility of additional dust and temporary lane restrictions.


Public Meetings & Information Centres