Thornbury Pier

Project Information

The Thornbury Pier is a significant waterfront amenity that typically sees large numbers of visitors throughout the summer months for uses such as swimming, fishing, and viewing Georgian Bay. As the pier deck deteriorated, Town staff worked with the owner of the structure, Department of Fisheries and Oceans Canada, to purchase and install matting to cover the surface of the pier and eliminate tripping hazards. This solution worked for many years until high water levels started moving the matting and then ice during the winter season damaged the matting and the edging even further until it was no longer feasible to repair and replace the matting.

Engineering Services were retained and following the report by AECOM in 2020, it was recommended that a full deck replacement take place due to the condition of the deck. After the existing decking is removed, areas under the pier that are void of granular stone will be replaced, conduits will be replaced and minor welding repairs will occur. 

After a Request For Proposal for the construction was posted in early 2021, the contract was awarded to Brook Restoration Ltd. Construction began on Friday, March 12th, 2021. 

Construction has been fully mobilized and hoarding has been installed to prevent material from falling into the water as they begin to jackhammer the concrete. The structural steel within the concrete pre-dates conventional re-bar and is larger which caused some unforeseen challenges but is now being removed. As of March 24th, approximately 40' of the deck has been removed. 

Project Updates

The Town of The Blue Mountains would like to advise residents that the Thornbury Pier Resurfacing Project has been delayed following public health guidance and in response to the required measures to be taken related to COVID-19. For more information, please read the following press release: Notice- Thornbury Pier Project Facing Temporary Delay