October 21, 2021
Phase 1 construction has been completed. Phase 2 of construction is scheduled to begin in the spring of 2022.
September 20, 2021
SMRS Construction is continuing to drill in the new watermain this week on Louisa Street East and Wellington Street South. They are completing final clean-up on Lansdowne Street North and Napier Street East. Only final watermain connections and clean-up remain on Arthur Street East. The contractor is expecting to wrap up the remainder of the project in the next few weeks.
September 10, 2021
SMRS Construction has been installing new watermain on Arthur Street East this week. They will test, commission, and connect the new watermain to the rest of the Town’s distribution system next week. Napier Street East and Lansdowne Street North were paved last week, and are receiving final touch ups.
August 23, 2021
SMRS Construction is completing the watermain installation and commissioning process on Lansdowne Street North this week. They are also fine grading Napier Street East to prepare it for paving. They will be moving on to start watermain construction on Arthur Street East nearer the end of this week.
August 9, 2021
A majority of the new watermain has been installed on Napier Street. Work will continue on Napier Street including at the Russell Street intersection. Work is expected to be completed on Napier Street by the end of the week of August 9 or early the week of August 16. The watermain at Bay and Lansdowne will be installed the week of August 9.