July 9, 2026 - Schedule updates for 6th Line
Arnott Construction has updated their anticipated schedules for the rehabilitation of the 6th Line Bridge. They are expecting to begin work on Wednesday, July 15 with a full road closure in place until August 6. At this time they will be pausing work on the 11th Line Bridge. They expect to return to the 11th Line site on Monday, July 20 to resume work on the superstructure. Current anticipated schedules for 12th Sideroad, Victoria Corners and Red Wing remain unchanged.
June 23, 2026 - Schedule updates for 11th Line and Red Wing Bridges
Arnott Construction has completed rehabilitation work on the Slabtown Bridge, including most upgrades to the guiderail and end treatments. They will be on site one day this week to complete remaining guiderail work.
Arnott has also updated their anticipated schedules for the 11th Line Bridge and Red Wing Bridge. Due to delays on some in-water works in Red Wing, they now expect to start work on the 11th Line Bridge the week of June 29. The 11th Line Bridge is anticipated to remain open while work is completed under the structure, and then the temporary full closure will be put in place once surface work begins. Rehabilitation work on the Red Wing Bridge has been pushed back to September 15 to October 7.
June 12, 2026 - 10th Line culvert complete, Slabtown Bridge rehabilitation continues
Arnott Construction has completed work on the 10th Line culvert. For the week of June 15, they will continue with rehabilitation work on the Slabtown Bridge, including guiderail installation. Single-lane traffic control will be in place for duration of this work. Preliminary work on the Red Wing Bridge is planned for next week as well, including required tree removals. This work will be completed with single-lane traffic restrictions in place in advance of the temporary closure and detour which is tentatively schedule to be in place the week of June 22, 2026.
June 5, 2026 - Remaining work on 10th Line and work beginning on Slabtown Road
Arnott Construction will be continuing with work on the 10th Line culvert until Friday, June 12 to complete installation of the guide rail. They will also be continuing on schedule with rehabilitation work beginning Monday, June 8 on the Slabtown Bridge. Single-lane traffic control will be in place for duration of this work. They may also begin preliminary work on the Red Wing Bridge later next week with single-lane traffic restrictions in place in advance of the temporary closure.