Other Bridges and Culverts
Rehabilitation works are expected to be completed on four additional structures in 2026. These structures will remain open to traffic with alternating single-lane restrictions.
1. 10th Line Culvert
Anticipated Construction Period: June 1-5
The 10th Line Culvert is an elliptical multi-plate corrugated steel pipe. Rehabilitation works are expected to include the installation of a proper guide rail on both approaches and across the structure.
2. Slabtown Bridge
Anticipated Construction Period: June 8-24
The Slabtown Bridge is a concrete deck on a prefabricated steel truss bridge. Rehabilitation works are expected to include modifications to the approach guide rail to improve safety.
3. 12th Sideroad Bridge
Anticipated Construction Period: August 17-28
The Slabtown Bridge is a concrete deck on a prefabricated steel truss bridge. Rehabilitation works are expected to include concrete repairs and modifications to the approach guide rail to improve safety.
4. Victoria Corners Bridge
Anticipated Construction Period: August 31 to September 14
The Victoria Corners Bridge is a concrete rigid frame bridge. Rehabilitation works are expected to include repairs to the approaches, installation of signage and improvements to the guide rails.