July 29, 2022
E.C. King Construction is demobilizing from the site and has removed all fencing and construction materials. Please avoid walking on the fresh sod for at least 2-3 weeks to allow it to take root. Construction crews may return from time to time to water the landscaping and rectify any deficiencies that are found.
June 30, 2022
Paving, line painting, lighting and signage have all been completed. The parking lot will be operational for the July long weekend, with fencing and traffic barrels left up in some areas for pedestrian safety. Construction crews will return over the coming weeks to complete the landscaping work.
June 27, 2022
Construction of the Arthur Street West Parking Lot is proceeding well. Concrete curbs and sidewalks have been installed. The contractor is planning to pave the parking lot and road cut on Monday and Tuesday of this week, then will transition to landscaping work.
June 20, 2022
Construction of the Arthur Street Municipal Parking Lot is continuing on schedule. Storm sewer work is nearing completion and light post bases have been installed. Upcoming construction work will include installation of concrete curbs, completion of base preparation, fine grading, and paving.
June 13, 2022
This week's construction plan includes storm sewer work, installation of conduit for EV charging stations and final preparations for installation of the concrete curbs. The contractor is also planning to install and connect the Oil/Grit Separator to the existing storm sewer system on Monday. This will require closure of the south lane on Arthur Street. Traffic will be shifted to maintain two lanes of travel. The south sidewalk will remain closed during this work.
June 6, 2022
Construction of the Arthur Street West Parking Lot is proceeding well. To date, 95% of the sub-base preparation and granular sub-base is complete, as well as the majority of the stormwater management system. Construction activities scheduled for this week include placement of the "A" granular base, and preparation for curb and sidewalk installation.
May 30, 2022
Construction activities scheduled for this week include the completion of the storm sewer system, and preparation for curb and sidewalk installation which is scheduled to begin the week of June 6.
May 24, 2022
Construction of the Arthur Street West Parking Lot remains on schedule. Work this week is scheduled to include the continuation of the internal storm sewer system, and the connection to the external storm sewer. Two lanes of traffic will be maintained at all times while this work is being completed.
May 16, 2022
Construction of the Arthur Street West Parking Lot is proceeding on schedule. Work this week is scheduled to include continued excavation and preparation of the granular sub-base, as well as the start of the installation of the parking lot’s storm sewer system.
May 9, 2022
The construction schedule for this week includes demolition of the shed located at the south corner of the lot, site stripping and clearing, and fence installation along the south property line. Residents should be aware of the additional noise, dust and disturbances these activities may cause.