October 8, 2021
Construction has been completed. Full road repaving in this area will be considered, pending budget approval by Council, upon completion of the Tyrolean Village Watermain Replacement and Wastewater Servicing Project.
September 29, 2021
Paving on Craigmore Crescent and Tyrolean Lane will be completed the week of October 4, 2021. At this time, only the lanes disturbed by the recent work will be repaved. Full road repaving will be considered, pending budget approval by Council, upon completion of the Tyrolean Village Watermain Replacement and Wastewater Servicing Project scheduled to begin in spring 2022.
September 15, 2021
Arnott Construction has decommissioned the temporary watermain. All affected residents have now been switched over to the new Town infrastructure. The team is working on Birch View Trail this week installing a new water chamber and finalizing grading within the project areas.
September 1, 2021
Arnott Construction is commissioning the new watermain on Craigmore Crescent and Tyrolean Lane this week. Next week the crew will be connecting the new watermain to the Town water distribution system and decommissioning the temporary watermain.
August 17, 2021
Work on Craigmore Crescent has been completed and construction has begun on Tyrolean Lane. Work is expected to be completed on Tyrolean by the end of the week of August 16. Once finished on Tyrolean, crews will move to Birch View Trail and begin work.
July 23, 2021
All residents impacted by current construction have been moved onto a temporary water supply. Arnott Construction Ltd. will begin installing the new watermain on Craigmore Crescent beginning on July 26. Drilling for water services under the roadway will also begin.
July 12, 2021
Arnott Construction will be placing some of the homeowners on Craigmore Crescent (between Grey Road 19 and Tyrolean Lane) and Tyrolean Lane (between Craigmore Crescent and Arlberg Crescent) onto a temporary watermain. Work will also be completed on Birch View Trail, Crossan Court and Brooker Boulevard. These affected areas may see water service disruption for up to eight hours on Tuesday, July 13 and Wednesday, July 14 from 8am to 4pm.
June 28, 2021
This week, Arnott Construction will be commissioning the new watermain they installed last week on Craigmore Crescent at Settler's Way. They will then move to Birch View Trail and start installing the new watermain from Brooker Boulevard, north to Arlberg Crescent.
June 21, 2021
Arnott Construction Ltd. will continue with the watermain installation on Craigmore Crescent and Settler's Way. They will also perform a watermain shutdown on Brooker Drive to allow them to start the watermain installation on Birch View Trail the following week. Residents could be without water for up to eight hours on Wednesday, June 23 and Thursday, June 24 from 8 am to 4 pm. Notices will be sent to the affected residences 48 hours in advance.
View Resident Notice
June 7, 2021
Arnott Construction is beginning mobilization for the Pressure Zone 4C Water Distribution Construction project. Temporary water supply disruptions and road closures may occur during the construction process.
Traffic will be restricted to local traffic and Emergency Services from 7am to7 pm, Monday to Friday, from June 7 to October 29, 2021 in the following areas:
- Craigmore Crescent at County Road 19
- Tyrolean Lane at Craigmore Crescent
- Craigmore Crescent at Settlers Way
- Birch View Trail at Arlberg Crescent