Image
Aerial view of Thornbury Wastewater Treatment Plant under construction with escarpment in background

Thornbury Wastewater Treatment Plant Expansion

On this page:
1. Project Updates
2. Staff Reports & Council Decisions
3. Map of Project Area
4. Progress Photos
5. Outfall Installation
6. Quarterly Progress Reports 

The Thornbury Wastewater Treatment Plant was completed in 1994, with a rated capacity of 3580 m3/day. This project will include the construction/installation of all equipment required for operation of the Extended Aeration treatment system to increase capacity to 5,330 m3/day.

Step 1

  • Civil site prep work

Step 2

  • Addition of one extended aeration tank, including aeration system, required accessories, and alum addition 
  • Addition of one clarifier and associated mechanical system
  • Increase the current Ultraviolet disinfection system to meet 5,330 m3/day
  • Replacement of existing air blowers, including required valves, controls, instrumentation and distribution piping
  • Additional 14,000 m3/day mechanical screen and associated hardware to be added
  • Incorporate energy efficiency throughout the plant
  • Construction of a new outfall pipe to Georgian Bay

Expansion of the plant was approved as part of the 2020 Town Budget. It is anticipated that the detailed design will be completed in Q3 2022. Construction will be completed in two steps to allow for scheduled advancements. The first step is scheduled to be completed in Q3 2022, with the second step beginning immediately afterwards. The project is expected to be completed in Q4 of 2026.

Why Now?

To replace end-of-life equipment and ensure the Thornbury Wastewater Treatment Plant is capable of providing reliable service in line with the forecasted growth of the community.


Project Updates

March 25, 2024

The Town's contractor has been working on upgrades to multiple systems throughout the plant. The headworks, aluminum sulphate system and ultraviolet disinfection system are all being upgraded to meet the needs of the plant's final capacity targets..


Staff Reports & Council Decisions


Map of Project Area

Site plan for Thornbury Wastewater Treatment Plant Expansion

Progress Photos


Outfall Installation

A new outfall is to be constructed to accommodate the approved increased capacity to the Thornbury Wastewater Treatment Plant. The new outfall alignment extends from the Treatment Plant to the shoreline of Georgian Bay, following within the existing Grey Street road allowance. The outfall alignment includes the crossings of King Street East (MTO Highway 26 at Grey Street) and at Bay Street. 

The outfall extends 1500 m to the north from the shoreline into Georgian Bay. The first 600 m of the outfall pipe from the shoreline will be dredged, and the remaining 900 m will lay on the lakebed in the deeper water. Due to fisheries windows, the marine portion of the outfall will need to begin no earlier than July 15, 2025, and be completed no later than September 30, 2025.

View Notice

Map showing general location of outfall installation off the shoreline of Georgian Bay
Approximate extents of in-water construction work

Quarterly Progress Reports

Q1 2025

Project Scope: Within expanded scope
Project Schedule: Within revised schedule
Project Budget: Within revised budget

Notes: Lora Bay Park was selected by Council as site for assembly of new outfall pipe.