The Town of The Blue Mountains would like to advise residents that Brook Restoration Ltd. has resumed work on the Thornbury Pier Resurfacing Project after a temporary shutdown due to COVID-19 Public Health Protocols.
As a result of this unexpected delay, the project is now scheduled to be completed by June 25, 2021. Project updates will be posted on the Thornbury Pier Resurfacing project webpage on the Town website: https://www.thebluemountains.ca/thornbury-pier.cfm
“I would like to thank all residents for their understanding and patience caused by this unexpected delay,” explained Ryan Gibbons, Director of Community Services. “Although there is an understandable delay in the original project schedule, the contractor is confident that the new schedule is achievable, which will open the pier ahead of the summer season.”