Image
Pipes extending out into Georgian Bay from shoreline

Outfall Pipe Assembly and Installation

Upcoming Community Information Session

A Community Information Session will be held on Friday, August 28, 2026 to provide an overview and update on the project. The meeting will include a presentation from the Town's engineering consultant and a question and answer session. All those interested in the project are invited to attend.

View Meeting Details View Notice

On this page:
1. Project Updates
2. Outfall Installation Details
3. Lora Bay Park Site Map
4. Staff Reports & Council Decisions
5. Public Consultation
6. Frequently Asked Questions 

The Town is upgrading the Thornbury Wastewater Treatment Plant Outfall Pipe to allow the plant to meet its full capacity. This outfall will be installed off the north end of the Grey Street road allowance, and run 1.5 km into Georgian Bay. The pipes will be assembled in 200m lengths on the shore, and then floated until final assembly can be completed. 

In 2024, Town Staff, along with the Town’s Consultant, Arcadis, did a wide-ranging search of potential staging sites for the outfall pipe. The sites were evaluated based on accessibility, space for storage, assembling and construction equipment/facilities, water depth, protected waters and site security. Through the evaluation process, Lora Bay Park was deemed the only suitable site. Although the public use of the park would be interrupted for the summer, using Town lands to construct the offshore pipe would eliminate the costs associated with a lease agreement of a private landowner, therefore reducing the overall cost of construction. 

The shoreline of Georgian Bay has a restricted activity window for the protection of spawning fish that extends between September and July. This window provides approximately 2.5 months to conduct any work in Georgian Bay. Pre-construction preparation will be conducted before the window opens to ensure that work on the shoreline can be completed on time. Public access to Lora Bay Park will be prohibited during the pre-construction and construction window.

Why Now?

The Town needs to upgrade the Thornbury Wastewater Treatment Plant Outfall Pipe to allow the plant to meet its full capacity.


Project Updates

Construction Updates

August 14, 2026 - Weekend work plan and lookahead schedule

The contractor expects to work extended hours from 1 p.m. to 5 p.m. this Saturday to continue in-water dredging, weather and water conditions permitting. They also expect to be performing general site maintenance activities at Lora Bay Park. Looking ahead to next week, the primary areas of focus will be the continuation of dredging and the installation of concrete ballast weights.

Other Project Updates

August 18, 2026 - Upcoming Staff Report regarding working hours

A Staff Report is scheduled to be presented to Committee of the Whole on Tuesday, August 25. Details can be found in the Staff Reports section of this page.

View Staff Reports


Outfall Installation Details

A new outfall is to be constructed to accommodate the approved increased capacity to the Thornbury Wastewater Treatment Plant. The new outfall alignment extends from the Treatment Plant to the shoreline of Georgian Bay, following within the existing Grey Street road allowance. The outfall alignment includes the crossings of King Street East (MTO Highway 26 at Grey Street) and at Bay Street. 

The outfall extends 1500 m to the north from the shoreline into Georgian Bay. Approximately the first 600 m of the outfall pipe from the shoreline will be dredged, and the remaining segment will lay on the lakebed in the deeper water. Due to fisheries windows, the marine portion of the outfall will need to begin no earlier than July 1, and be completed no later than September 30.

Turbidity curtains have been instilled to minimize the spread of suspended sediment. Due to the nature of the lakebed (hard clay) and the fact that the curtain does allow for some water movement, discolouration of the water on the outside of the curtain cannot be avoided. The contractor has real-time turbidity monitoring buoys set up on the east and west side of the dredging site. As the dredging progresses offshore into the sand and gravel lakebed, turbidity is expected to be reduced.

Map showing general location of outfall installation off the shoreline of Georgian Bay
Approximate extents of in-water construction work

Lora Bay Park Site Map

Sample site map of Lora Bay Park

Staff Reports & Council Decisions

August 25, 2026 - Extended working hours for offshore work

Staff Report OPS.26.047 is scheduled to be presented to Committee of the Whole on Tuesday, August 25. The report is being presented to inform Council that the contractor will be working extended hours offshore, beyond the Town's municipal boundary. The Town’s Noise By-law cannot regulate offshore activities solely because noise generated by those activities may be audible from Thornbury. The contractor has previously been approved to work extended hours on Saturdays from 1:00 p.m. to 5:00 p.m. Despite this extension, there remains a risk that the work may not be able to be completed within the permitted timeframe. 

The contractor has submitted a request for additional working hours including Monday to Friday from 7:00 a.m. to 9:00 p.m., Saturdays from 7:00 a.m. to 7:00 p.m. and Sundays from 7:00 a.m. to 1:00 p.m. The intent is to use these additional hours primarily for less disruptive construction activities. The extended work period would be dedicated to offshore operations occurring a considerable distance from the shoreline, minimizing potential impacts to nearby residents. 

View Staff Report


Public Consultation

Community Information Session - August 28, 2026

A Community Information Session will be held on Friday, August 28, 2026 to provide an overview and update on the installation of the new treated eflluent outfall pipe for the Thornbury Wastewater Treatment Plant. The Town’s engineering consultant, Arcadis, will be giving a presentation outlining the outfall installation process and the planned site restoration activities. Time will be held for a Question & Answer Session at the end of the meeting. The meeting will be recorded and posted to the project page for anyone unable to attend in person. If you are unable to attend the meeting in person, but have questions that you would like asked on your behalf during the Q&A, please email them to communications@thebluemountains.ca

Date: Friday, August 28, 2026 
Time: 1-2 p.m. 
Location: Town Hall, 32 Mill Street, Thornbury

View Notice

Lora Bay Park Restoration

Consistent with Council direction, a Staff Report is expected to be brought forward later this year to consider an approach to park revitalization. This could lead to an opportunity to make improvements as restoration works occur, or folding engagement and visioning through the development of the Parks, Open Spaces and Trails Master Plan that will be commencing this year. To be notified of any future public consultation opportunities regarding the project, please subscribe to the project email list.

Subscribe


Frequently Asked Questions