August 12, 2026 - Transition to barge dredging underway
The Town's contractor has reached the stage of the dredging where they have begun to transition to excavating from a barge. A temporary in-water berm has been constructed from clear stone to serve as a work platform for the dredging up to this point. This berm has allowed the machinery to stay out of the water while completing the shallow dredging, minimizing contamination from grease and other foreign substances that might be present on the excavator. The contractor is currently completing the work associated with the temporary berm, and it is anticipated that the dredging operation will fully transition to the barge within the next week.
The clear stone used to construct the berm will be removed following completion of this portion of the work, and the recovered stone will be reused as part of the required pipe bedding. Additional material will be placed on top of the bedding to prevent it from washing up onto the shore. Following installation of the new outfall, the shoreline and work area will be restored in accordance with the project requirements.
August 7, 2026 - Dredging resumes along with stockpiling of clear stone
The Town's contractor has completed installation of the modified turbidity curtain layout, and has resumed dredging operations. They have also begun stockpiling clear stone and are using it to build a temporary in-water berm. The clear stone will be used for bedding and backfilling around the buried section of the new outfall pipe when it's installed. Clear stone deliveries are expected to continue until the beginning of September at both Lora Bay Park and the Grey Street North site.
The contractor expects to work extended hours from 1 p.m. to 5 p.m. this Saturday with site maintenance being completed at Lora Bay Park, and dredging continuing at the Grey Street North site, pending water and weather conditions.
July 31, 2026 - Limited weekend work plan
In accordance with Council's direction, the Town's contractor will be limiting working hours this weekend to those allowed by the Town's Noise By-law. They plan to work 8:00 a.m. to 1:00 p.m. on Saturday, August 1, and a full day 7:00 a.m. to 7:00 p.m. on Monday, August 4. Planned work activities for Saturday include pipe fusing and site maintenance at Lora Bay Park, and turbidity curtain installation off the Grey Street road allowance. In-water dredging is currently expected to resume on Monday, August 4, weather and water conditions permitting.
July 30, 2026 - Water sampling results and pipe sinking in Lora Bay
The Town has received analysis results of water samples taken on Monday, July 20 from two locations at the Grey Street North installation site. The analysis measures total suspended solids which is a standard gauge of turbidity and water quality. Measured quantities were 15 mg/L north of the dredging zone and 35 mg/L south of the dredging zone. The Town is working with an independent Environmental Consultant to provide the review and feedback of the analysis.
View Results
At Lora Bay Park, Deepsix has partially filled the staged pipe with water to position it just below the water surface. This is a planned measure designed to reduce the effects of wave action by allowing wave energy to pass over the pipe rather than be resisted by it. Additional visual markers and buoys are being installed to clearly identify the pipe's location for residents and recreational watercraft operating in the area.
July 30, 2026 - Approval of amended construction plan
The amended construction plan formulated by the Town's contractor has been reviewed and approved by the Town’s engineering consultant, the Ministry of Natural Resources, the Department of Fisheries and Oceans, and local Conservation Authorities.
The turbidity curtain will be redeployed in a modified configuration to support completion of the remaining dredging work. The revised configuration will place remaining, usable curtain sections along both sides of the dredging corridor. The offshore end will remain open to reduce pressure from wind and waves, improving the system’s resilience during changing lake conditions. The contractor plans to begin reinstalling the turbidity curtain system and resuming dredging as early as Thursday, July 30, pending suitable weather and water conditions.
Maintaining environmental and public health remains paramount in the amended plan. Continuous turbidity monitoring will remain in place during dredging. If the monitoring system detects turbidity levels in exceedance of approved thresholds, response actions will be implemented, up to and including temporary suspension of dredging. The Town has also engaged a third-party consultant to complete water quality testing periodically along the shoreline outside the dredging corridor.
More details can be found in the full media release linked below.
View Media Release
July 24, 2026 - Update on next steps and weekend work plan
Following the weather incident that occurred on the weekend of July 18, the Town continues to work with its contractors and engineering consultant to formulate a plan to resume installation of the new outfall without impacting the overall project deadline. The Town has been in contact with the Ministry of Natural Resources, Department of Fisheries and Oceans, Conservation Authorities and other agencies that will need to review and approve the amended plan. Details will be shared once the plan has been finalized and approved at all levels.
The contractor expects to work extended hours from 1 p.m. to 5 p.m. this Saturday to continue pipe fusing at Lora Bay Park and to perform general maintenance at the Grey Street North site. Water quality testing was completed at the Grey Street North site earlier this week. Results will be shared to the project page when available.
July 17, 2026 - Extended Saturday hours for shoreline dredging
The contractor expects to work extended hours from 1 p.m. to 5 p.m. this Saturday to continue shoreline dredging, weather and water conditions permitting. They currently have approximately 70 metres of the dredging completed. Pipe fusing is also expected to restart at Lora Bay Park next week following delivery of materials.
July 10, 2026 - Turbidity monitoring alert
Earlier today, the Town's contractor was alerted of excess turbidity in the water in the area around the dredging site. They inspected the turbidity curtains and identified a minor failure which was immediately secured. The turbidity curtain installation includes a monitoring system which will continue to alert staff of any future issues.
July 9, 2026 - Extended Saturday hours for shoreline dredging
The contractor expects to work extended hours from 1 p.m. to 5 p.m. this weekend to continue shoreline dredging from the Grey Street North road allowance, weather and water conditions permitting. In accordance with Council's direction, no work will be conducted on Sunday.
July 8, 2026 - Shoreline dredging to begin this week
Dredging for the installation of the offshore section of the new outfall pipe at the Grey Street North road allowance is expected to begin on Thursday, July 9. Turbidity curtains have been installed in the Bay to prevent sediment from drifting in the currents once dredging begins. A subcontractor was on site today completing fish rescues from within the curtained area. At Lora Bay Park, pipe fusing activity will temporarily pause as the contractor waits on delivery of additional materials.
July 2, 2026 - In-water Work Permit window opens and weekend work at Lora Bay Park
The Town's permitted window for in-water work has opened as of July 1, and the marine work contractor has begun placing anchors and equipment in the water off the north end of the Grey Street road allowance. The contractor has also informed the Town that they will be working extended hours from 1 p.m. to 5 p.m. at Lora Bay Park to complete pipe fusing on July 4, July 11 and July 18. No work will be conducted on Sundays over these weekends.
June 1, 2026 - Contractor mobilizing to Lora Bay Park
Clearway Construction has begun mobilizing to Lora Bay Park to start the assembly of the new outfall pipe for the Thornbury Wastewater Treatment Plant. They will be working this week to install security fencing and place equipment.