Image
Excavator parked in front of site on Bay Street East

Bay Street East Reconstruction

On this page:
1. Project Updates
2. Staff Reports & Council Decisions
3. Public Consultation
4. Map of Project Area
5. Quarterly Progress Reports
6. Frequently Asked Questions 

The 2021 Town Budget included funding for a capital project intended to make upgrades to the Craigleith Main Sewage Lift Station. In May of 2022, Town Council approved a motion to increase the scope of the project to include upgrades to the Mill Street Sewage Lift Station and installation of an additional sanitary forcemain along Bay Street from Mill Street to Grey Street.

The Town’s Asset Management Plan indicates that the underground infrastructure on Bay Street in this location is in poor to very poor condition and is approaching the end of its useful life. The existing sanitary sewer and watermain are both made of asbestos cement, and both experience significant leakage issues. The installation of the secondary forcemain will involve road excavation that is likely to result in many more leaks as the ground shifts and settles. Considering that Bay Street from Mill Street to Grey Street will need to be significantly disturbed for the installation of the forcemain, this provides a great opportunity to reconstruct the entire road. This will ensure that the watermain, sewers and stormwater systems are adequate for the next 50-75 years. Addressing leaking watermains and sewers reduces the burden on both the water and wastewater systems, freeing up needed capacity and allowing more connections to current infrastructure.

Why Now?

The existing watermain and gravity sewer are approaching end of life, and a secondary forcemain is required between the Mill Street Sewage Pumping Station and the Thornbury Wastewater Treatment Plant to handle planned growth in the community.


Project Updates

February 26, 2026 - Workplan for start of March

For the week of March 2, Arnott Construction will be continuing with the installation of the new sanitary sewer, watermain and storm sewer between Mill Street and McAuley Street. Under the supervision of a certified Arborist, the contractor will also be completing trimming of tree roots located within the excavation limits to minimize the impact on trees that are to be retained. This trimming work is expected to continue over the next few weeks. EPCOR will also be continuing with utility pole relocation between Elgin Street and Grey Street. 


Staff Reports & Council Decisions

March 17, 2026 - Request for temporary relief from Noise By-law for Grey Street work

Staff Report OPS.26.015 is scheduled to be presented to Committee of the Whole on Tuesday, March 17, 2026. The report requests Council approval for temporary relief from the Town's Noise By-law to allow for the completion of work at the intersection of Grey Street and Highway 26. 

Staff have prepared a plan which would see the Town's contractor work 24 hours a day for a period of four days in May to complete the installation of the forcemain and outfall across Highway 26. The Contractor has estimated that if the work was completed during normal construction hours it would take approximately 2-4 weeks. By working 24 hours a day, the work can be completed in four days, avoiding extended traffic congestion on Highway 26 and minimizing the impact on residents.

View Report OPS.26.015


Public Consultation

Public Information Centre #2 - December 17, 2024

The second Public Information Centre was held to review and answer questions about the 60% design, and to provide an overview of the next steps in the project.

View Meeting Recording

View Presentation Deck

View Notice of PIC 
 


Map of Project Area

Map of Bay Street East project area

Quarterly Progress Reports

Q4 2025

Project Scope: Within scope
Project Schedule: Within schedule
Project Budget: Budget revised

Notes: Council approved an additional $19 million for untendered work which includes an expansion and upgrade of the Mill Street Sewage Pumping Station. 


Frequently Asked Questions