Substandard Watermain Replacement Phase 2

On this page: 
1. Project Updates
2. Public Meetings & Information Centres
3. Map of Project Area
4. Quarterly Progress Reports

The Town of The Blue Mountains has identified thirteen sections of watermain that have been classified as substandard and require upgrade. Phase 1 of the Substandard Watermain Replacement Program was completed in 2021. Phase 2 construction is anticipated to be completed in the summer of 2023.

Two areas have been identified by Town staff as part of Phase 2 for construction in 2023. These areas are:

  • Napier Street West in Thornbury from Victoria Street South to 96 Napier Street West
  • Woodland Park Road in Camperdown

The construction tender for Phase 2 work closed in mid June, and was awarded to SMRS Construction. Construction began in August of 2023, and is expected to be completed in October of 2023.

Why Now?

The project will improve water movement, firewater flow, reduce opportunities of stagnant water, increase water quality, and provide operational savings.


Project Updates

October 2, 2024

SMRS Construction is scheduled to return to Woodland Park Road on Friday, October 4 to complete culvert work between 157 and 165 Woodland Park Road. The work will require temporary lane closures. Access through the construction area will be maintained for emergency vehicles only. Impacted properties will be notified directly by the contractor.


Public Meetings & Information Centres

There were no Public Meetings or Information Centres held for this project.


Map of Project Area

Location of work sites for Substandard Phase 2

Quarterly Progress Reports

Q4 2023

Project Scope: Within scope
Project Schedule: On schedule
Project Budget: Within budget

Notes: Substantial Performance was reached in October 2023 and the project has entered the warranty period.