Construction Tender Awarded for 2026 Bridge and Culvert Capital Works

Map showing locations of structures
Press Releases
Maintenance / Service Disruptions

The Town of The Blue Mountains would like to advise residents that Arnott Construction has been awarded the construction tender for the Town’s 2026 Bridge and Culvert Rehabilitation works. 

The Bridge and Culvert Rehabilitation program is a multi-year effort to repair deficiencies and extend the lifespans of a number of critical, Town-owned structures. A total of seven bridges and culverts have been identified for rehabilitation in 2026. Structures have been prioritized based on existing condition assessments and the scope of work required. Three of the seven sites will require full closures while the work is being completed, while the remaining sites will only require alternating single-lane restrictions. 

The contractor has prepared a preliminary schedule which would see all the work completed between June 1 and September 29, pending weather and conditions. Work is planned to be staggered so that only one structure is impacted at a time.

StructureTraffic ImpactsEstimated Construction
1. 10th Line Culvert (C202)Alternating single-lane closuresJune 1-5, 2026
2. Slabtown Bridge (B15)Alternating single-lane closuresJune 8-24, 2026
3. Red Wing Bridge (B7)Temporary full closureJune 25 to July 23, 2026
4. 6th Line Bridge (B8)Temporary full closureJuly 24 to August 14, 2026
5. 12th Sideroad Bridge (B7)Alternating single-lane closuresAugust 17-28, 2026
6. Victoria Corners Bridge (B12)Alternating single-lane closuresAugust 31 to September 14, 2026
7. 11th Line Bridge (B19)Temporary full closureSeptember 15-29, 2026

The Town has published a dedicated project web page where updates will be posted as work progresses. Individual email lists have also been created for those with interest in the Red Wing Bridge, 6th Line Bridge and 11th Line Bridge. Any members of the public with specific interest in these sites are encouraged to subscribe to receive updates regarding the schedule and ongoing work on these three structures. 

View Project Web Page 

For more information, please contact: 

Chris Thompson 
Senior Infrastructure Capital Project Coordinator 
Operations Department 
(519) 599-3131 ext. 304