Image
Lora Bay Park green space

Outfall Pipe Assembly at Lora Bay Park

On this page:
1. Project Updates
2. Staff Reports & Council Decisions
3. Public Consultation
4. Map of Project Area
5. Outfall Installation
6. Frequently Asked Questions 

The Town is upgrading the Thornbury Wastewater Treatment Plant Outfall Pipe to allow the plant to meet its full capacity. This outfall will be installed off the north end of the Grey Street road allowance, and run 1.5 km into Georgian Bay. The pipes will be assembled in 200m lengths on the shore, and then floated until final assembly can be completed. 

In 2024, Town Staff, along with the Town’s Consultant, Arcadis, did a wide-ranging search of potential staging sites for the outfall pipe. The sites were evaluated based on accessibility, space for storage, assembling and construction equipment/facilities, water depth, protected waters and site security. Through the evaluation process, Lora Bay Park was deemed the only suitable site. Although the public use of the park would be interrupted for the summer, using Town lands to construct the offshore pipe would eliminate the costs associated with a lease agreement of a private landowner, therefore reducing the overall cost of construction. 

The shoreline of Georgian Bay has a restricted activity window for the protection of spawning fish that extends between September 30 and July 15. This window provides 2.5 months to conduct any work in Georgian Bay. Pre-construction preparation will be conducted before the July 15 window to ensure that work on the shoreline can be completed on time. Public access to Lora Bay Park will be prohibited during the pre-construction and construction window. At the completion of the construction of the outfall, restoration work for the park could potentially add benefits for the community, based on Council’s direction.

Why Now?

The Town needs to upgrade the Thornbury Wastewater Treatment Plant Outfall Pipe to allow the plant to meet its full capacity.


Project Updates

May 12, 2026 - Update on mobilization

The contractor has provided the Town with an updated schedule. They currently plan to mobilize to Lora Bay Park during the first week of June to begin site preparation. Consistent activity at the Grey Street road allowance in Thornbury is expected to begin in mid June.


Staff Reports & Council Decisions

April 28, 2026 - Approval of relief from Noise By-law

Staff Report OPS.26.024 was presented to Committee of the Whole on Tuesday, April 28. The report provides an update on the status of the Outfall Assembly and Installation project, and requests that Council grant relief from the Town's Noise By-law to allow for work to be completed on weekends as required to remain within the in-water construction window allowed by the MNRF. Committee heard the report and passed a motion that will allow for work to be completed on a maximum of three weekends over the exemption period between May 15 and September 31. The Town will be utilizing the project email lists for this page and the Bay Street East Reconstruction project to notify the public of the specific weekends when additional work will be occurring. 

Presentation of the report begins at the 1:42:40 mark of the meeting recording. The Committee motions were adopted by Council at their meeting on Monday, May 11.

View Meeting Recording


Public Consultation

Consistent with Council direction, a Staff Report is expected to be brought forward later this year to consider an approach to park revitalization. This could lead to an opportunity to make improvements as restoration works occur, or folding engagement and visioning through the development of the Parks, Open Spaces and Trails Master Plan that will be commencing this year. To be notified of any future public consultation opportunities regarding the project, please subscribe to the project email list.

Subscribe


Map of Project Area

Sample site map of Lora Bay Park

Outfall Installation

A new outfall is to be constructed to accommodate the approved increased capacity to the Thornbury Wastewater Treatment Plant. The new outfall alignment extends from the Treatment Plant to the shoreline of Georgian Bay, following within the existing Grey Street road allowance. The outfall alignment includes the crossings of King Street East (MTO Highway 26 at Grey Street) and at Bay Street. 

The outfall extends 1500 m to the north from the shoreline into Georgian Bay. The first 600 m of the outfall pipe from the shoreline will be dredged, and the remaining 900 m will lay on the lakebed in the deeper water. Due to fisheries windows, the marine portion of the outfall will need to begin no earlier than July 15, and be completed no later than September 30.

Map showing general location of outfall installation off the shoreline of Georgian Bay
Approximate extents of in-water construction work

Frequently Asked Questions