July 9, 2026 - Extended Saturday hours for shoreline dredging
The contractor expects to work extended hours from 1 p.m. to 5 p.m. this weekend to continue shoreline dredging from the Grey Street North road allowance, weather and water conditions permitting. In accordance with Council's direction, no work will be conducted on Sunday.
July 8, 2026 - Shoreline dredging to begin this week
Dredging for the installation of the offshore section of the new outfall pipe at the Grey Street North road allowance is expected to begin on Thursday, July 9. Turbidity curtains have been installed in the Bay to prevent sediment from drifting in the currents once dredging begins. A subcontractor was on site today completing fish rescues from within the curtained area. At Lora Bay Park, pipe fusing activity will temporarily pause as the contractor waits on delivery of additional materials.
July 2, 2026 - In-water Work Permit window opens and weekend work at Lora Bay Park
The Town's permitted window for in-water work has opened as of July 1, and the marine work contractor has begun placing anchors and equipment in the water off the north end of the Grey Street road allowance. The contractor has also informed the Town that they will be working extended hours from 1 p.m. to 5 p.m. at Lora Bay Park to complete pipe fusing on July 4, July 11 and July 18. No work will be conducted on Sundays over these weekends.
June 1, 2026 - Contractor mobilizing to Lora Bay Park
Clearway Construction has begun mobilizing to Lora Bay Park to start the assembly of the new outfall pipe for the Thornbury Wastewater Treatment Plant. They will be working this week to install security fencing and place equipment.