Lakewood Drive Reconstruction

On this page:
1. Project Updates
2. Staff Reports & Council Decisions
3. Public Consultation
4. Map of Project Area
5. Quarterly Progress Reports

The Town has identified Lakewood Drive for reconstruction due to deficiencies with the water distribution and sewage collection systems. The road was constructed in 1971, and is now due for replacement of the inground works. The road will be reconstructed and the ditches reshaped and cleared of trees.

One problem with the reconstruction is the lack of information regarding drainage outlets to the Bay. The Town does not have any drawings related to the road construction nor an overall subdivision grading plan. Tatham Engineering will be completing a stormwater study for the area, and will be presenting a number of preliminary proposed solutions to improve local drainage.

Through the 2023 Town Budget process, it was decided that the Town would complete the detailed engineering for Lakewood Drive this year, but to temporarily delay construction in favour if higher priority projects. At this time, there is no set schedule for the start of construction.

Why Now?

Lakewood Drive's water system is sub-standard, the main is a 3” pipe and there is only one hydrant at the east end of the road. The sanitary system has deficiencies and is leaking. The project is advancing as part of the Town’s capital asset management.


Project Updates

March 25, 2026 - Tree Inventory and Preservation Plan available

In advance of the second Public Information Centre, the Town's Consultant has completed and shared the current Tree Inventory and Preservation Plan. Removals will be required within the Town's road allowance throughout the project area to allow for the regrading of roadside ditches. Additional removals may be required in some areas for the installation of new service laterals to each property line.

View Plans 


Staff Reports & Council Decisions


Public Consultation

Public Information Centre #2 - March 26, 2026

The presentation deck and meeting recording from Public Information Centre #2 are available for review. A follow-up Staff Report will be prepared with an overview of what was discussed during the meeting, and will include a full summary of the public comments received. All comments received before the Staff Report deadline will be included with the report. 

View Presentation Deck

View Meeting Recording

View Notice


Map of Project Area

Map of Lakewood Drive Reconstruction project area

Quarterly Progress Reports

Q4 2025Project Scope: Within scope
Project Schedule: Within revised schedule
Project Budget: Within budget