Image
Traffic cones and excavation on Peel Street North

Peel Street North Reconstruction

On this page: 
1. Project Updates
2. Staff Reports & Council Decisions
3. Public Consultation
4. Map of Project Area
5. Quarterly Progress Reports
6. Frequently Asked Questions

The reconstruction of Peel Street has been identified as a project in the Town’s Development Charges Background Study (DCBS) for some time. The DCBS originally called for an Urban road cross-section with sidewalk, street illumination and street trees, but upon further review it was determined that the current road standards would not meet the project’s goals. A hybrid Rural/Urban Road with a 2.7m wide multi-use trail running parallel for pedestrians and cyclists was recommended for the reconstruction. 

Preliminary designs have provided the Town with a flexible outline for the project in the future. Features of the reconstruction will include an improvement to profile of Peel Street, which will improve sightlines for drivers and pedestrians. A replacement of the pavement structure was also recommended to meet current standards. 

A revised budget request sheet was included in the 2023 Proposed Town Budget for council consideration. This update accounted for current construction costs, and the proposed project scope to include a pedestrian bridge over the Little Beaver River. Unfortunately, shore stabilization issues became apparent along the Little Beaver River in the spring of 2025. Construction of the pedestrian bridge has been deferred until these issues can be addressed.

Why Now?

The Town is moving forward on the reconstruction of Peel Street as local development nears completion. 


Project Updates

November 6, 2025 - Update on remaining work

Walker Construction has completed installation of the new watermain, and is in the process of rebuilding the road base. In the coming weeks they plan to continue prepping for concrete curb and base asphalt, however this work could be impacted by weather and conditions. 

Due to a series of unexpected challenges that resulted in delays during the installation of the watermain, Walker will be required to carry some tasks forward to complete in the spring of 2026. At minimum this will include installation of the multi-use trail, surface asphalt, landscaping, ditching and tree planting.


Staff Reports & Council Decisions


Public Consultation

There are no more Public Meetings or Information Centres expected for this project. Comments can be directed to Council through the Clerks Department, and questions can be directed to the Project Manager through the Manager of Capital Projects.


Map of Project Area

Map of Peel Street Reconstruction Project Area

Quarterly Progress Reports

Q3 2025

Project Scope: Scope revised
Project Schedule: Behind schedule
Project Budget: Within revised budget

Notes: Delays resulted from issues finalizing design and commissioning watermain.


Frequently Asked Questions