Thornbury West Reconstruction Phase 1

On this page:
1. Project Updates
2. Staff Reports & Council Decisions
3. Public Consultation
4. Map of Project Area
5. Progress Photos
6. Quarterly Progress Reports
7. Frequently Asked Questions

At the beginning of the reconstruction project, the Town identified areas in Thornbury with infrastructure that is approaching 100 years old. The first two projects considered for infrastructure replacement were the Elma Street & Alice Street area, and the Victoria Street & Louisa Street area.

Through the preliminary engineering process, the Town identified that the two project areas were similar in nature. As a result, the two independent projects were combined and are now referred to as the "Thornbury West Phase 1 Reconstruction Project."

Final engineering work, which is the process where the design is completed and construction takes place, was awarded for the Elma Street & Alice Street area in 2019. However, the project faced unanticipated delays due to the COVID-19 pandemic. Construction will be divided into Phase 1A and Phase 1B to allow more time for the Town to review options for tree retention.

Phase 1A - Construction in 2022/2023

  • Victoria Street
  • Louisa Street, from Elma Street to Beaver Street
  • Beaver Street
  • 100m of Alice Street east of Victoria Street
  • Elma Street, from Arthur Street to Louisa Street

Phase 1B - Construction in 2025

  • Elma Street, from Louisa Street to Alfred Street
  • Lorne Street
  • Park Lane
  • Louisa Street, from Bruce Street to Elma Street
  • Remaining portion of Alice Street

Why Now?

Existing infrastructure requires replacement due to multiple watermain breaks, sewer deterioration, infiltration and excessive road cracking.


Project Updates

May 5, 2025 - Pipe work beginning on Louisa Street

The Town's contractor has nearly completed the first phase of topsoil, asphalt and concrete removal. They plan to begin excavation for pipe installations on Louisa Street on Tuesday, May 6. They will begin working from the intersection of Louisa Street and Elma Street, and proceed east towards Bruce Street. Residents or members of the public needing to access Louisa Street will need to enter from Bruce Street.


Staff Reports & Council Decisions

Since preliminary engineering began in 2016, the design of the Thornbury West Reconstruction project has evolved significantly through public consultation and Council direction. Details are available in the accordions below.


Public Consultation

There are no more Public Meetings or Information Centres expected for this project. Comments can be directed to Council through the Clerks Department, and questions can be directed to the Project Manager through the Manager of Capital Projects.


Map of Project Area

Map of Thornbury West project area

Progress Photos


Quarterly Progress Reports

Q1 2025

Project Scope: Within revised scope
Project Schedule: Schedule revised
Project Budget: Within budget

Notes: Construction tender for Phase 1B awarded in late March 2025.