Construction completed on Drake's Path

Drake's Path Wastewater Servicing Extension

On this page: 
1. Project Updates
2. Public Meetings and Information Centres
3. Map of Project Area
4. Progress Photos
5. Quarterly Progress Reports
6. Frequently Asked Questions
7. Related Documents

Drake’s Path was initially serviced with Town water in 1992 and recently has been identified within the Town's Water and Wastewater Servicing Extension Plan as an urban-designated area without full municipal services. In early November 2018, the project was moved forward in the Town’s Capital Plan.

The project will include:

  • wastewater servicing and service laterals to the property line of each property
  • minor drainage improvements and installation of a gravel turnaround
  • restoration to the existing conditions in the areas disturbed by the installation of the necessary infrastructure

The project was formally approved by Council through the 2019 budget process but was delayed due to transportation concerns in the area. In November 2020 the Town awarded the contract for the completion of the detailed engineering design and construction contract administration to WT Infrastructure Solutions Inc. It is anticipated that the detailed design will be completed in 2021, with construction following in the summer of 2022. Full road reconstruction is not being considered as part of this project.

Why Now?

Drake's Path was identified within the Town's Water and Wastewater Servicing Extension Plan as an urban-designated area without full municipal services. 


Project Updates

March 25, 2025 - Approval of By-law to impose capital charges

Staff Report CFS.25.014 was presented to Committee of the Whole on Monday, March 17. The report provided an overview of the Public Information Centre held on Thursday, March 6, and requested Council direction to prepare By-laws to impose the capital charges for Drake's Path, Price's Development and Birch View Trail using the Infrastructure Ontario interest rates as of March 12, 2025. Committee voted in favour of the staff recommendations, and this direction was adopted by Council at their meeting on Monday, March 24. The Town's Finance Department will be sending out the Payment Election Forms to benefitting property owners before the end of the month.

Presentation of the report begins at the 3:55:55 mark of the Committee meeting recording.

View Meeting Recording


Public Meetings and Information Centres

Public Information Centre - March 6, 2025

This Public Information Centre is being held to provide more information to benefitting properties about the proposed payment plan options for the wastewater servicing capital charges.

View Meeting Recording

View Presentation Deck

View Notice


Map of Project Area

Map of Drake's Path project area

Progress Photos


Quarterly Progress Reports

Q4 2022

Project Scope: Within scope
Project Schedule: On schedule
Project Budget: Within revised budget

Notes: Construction is complete and the project has entered a 12-month warranty period.