Image
New curb installed on Louisa Street

Thornbury West Reconstruction Phase 1

On this page:
1. Project Updates
2. Staff Reports & Council Decisions
3. Public Consultation
4. Map of Project Area
5. Progress Photos
6. Quarterly Progress Reports
7. Frequently Asked Questions

At the beginning of the reconstruction project, the Town identified areas in Thornbury with infrastructure that is approaching 100 years old. The first two projects considered for infrastructure replacement were the Elma Street & Alice Street area, and the Victoria Street & Louisa Street area.

Through the preliminary engineering process, the Town identified that the two project areas were similar in nature. As a result, the two independent projects were combined and are now referred to as the "Thornbury West Phase 1 Reconstruction Project."

Final engineering work, which is the process where the design is completed and construction takes place, was awarded for the Elma Street & Alice Street area in 2019. However, the project faced unanticipated delays due to the COVID-19 pandemic. Construction will be divided into Phase 1A and Phase 1B to allow more time for the Town to review options for tree retention.

Phase 1A - Construction in 2022/2023

  • Victoria Street
  • Louisa Street, from Elma Street to Beaver Street
  • Beaver Street
  • 100m of Alice Street east of Victoria Street
  • Elma Street, from Arthur Street to Louisa Street

Phase 1B - Construction in 2025

  • Elma Street, from Louisa Street to Alfred Street
  • Lorne Street
  • Park Lane
  • Louisa Street, from Bruce Street to Elma Street
  • Remaining portion of Alice Street

Why Now?

Existing infrastructure requires replacement due to multiple watermain breaks, sewer deterioration, infiltration and excessive road cracking.


Project Updates

October 2, 2025 - Pipe installation completed

Moorefield Excavating has completed installation of the new watermain, sanitary sewer and storm sewer. Sidewalks and curbs have also been installed on Louisa Street and on Elma Street between Louisa and Alice. Moorefield expects to continue with curb and sidewalk installation throughout the rest of the project area before the Thanksgiving weekend. Please note that access to driveways could be restricted for up to 72 hours following placement of curb and sidewalk to allow the concrete to cure. Once curbs and sidewalks are completed, they will begin final grading of the road surface in preparation for asphalt.


Staff Reports & Council Decisions

Since preliminary engineering began in 2016, the design of the Thornbury West Reconstruction project has evolved significantly through public consultation and Council direction. Details are available in the accordions below.


Public Consultation

There are no more Public Meetings or Information Centres expected for this project. Comments can be directed to Council through the Clerks Department, and questions can be directed to the Project Manager through the Manager of Capital Projects.


Map of Project Area

Map of Thornbury West project area

Progress Photos


Quarterly Progress Reports

Q2 2025Project Scope: Within revised scope
Project Schedule: Within revised schedule
Project Budget: Within budget

Frequently Asked Questions