Construction material staged on Victoria Street

Thornbury West Reconstruction Phase 1

On this page:
1. Project Updates
2. Public Meetings & Information Centres
3. Map of Project Area
4. Quarterly Progress Reports
5. Frequently Asked Questions

At the beginning of the reconstruction project, the Town identified areas in Thornbury with infrastructure that is approaching 100 years old. The first two projects considered for infrastructure replacement were the Elma Street & Alice Street area, and the Victoria Street & Louisa Street area.

Through the preliminary engineering process, the Town identified that the two project areas were similar in nature. As a result, the two independent projects were combined and are now referred to as the "Thornbury West Phase 1 Reconstruction Project."

Final engineering work, which is the process where the design is completed and construction takes place, was awarded for the Elma Street & Alice Street area in 2019. However, the project faced unanticipated delays due to the COVID-19 pandemic. Construction will be divided into Phase 1A and Phase 1B to allow more time for the Town to review options for tree retention.

Phase 1A - Construction in 2022

  • Victoria Street
  • Louisa Street, from Elma Street to Beaver Street
  • Beaver Street
  • 100m of Alice Street east of Victoria Street

Phase 1B - Construction in 2023 (est.)

  • Elma Street
  • Lorne Street
  • Park Lane
  • Louisa Street, from Bruce Street to Elma Street
  • Remaining portion of Alice Street

Why Now?

Existing infrastructure requires replacement due to multiple watermain breaks, sewer deterioration, infiltration and excessive road cracking.


Project Updates

August 15, 2022

Arnott Construction will be continuing with the installation of storm sewer on Beaver Street in addition to commissioning the new watermain. EPCOR will be relocating hydro lines at the entrance to Appleridge and at the intersection of Victoria Street and Louisa Street. The Town has also received a report from the vibration monitoring technician, and can confirm that peak vibration levels recorded over the past week are well within acceptable ranges.


Public Meetings & Information Centres

The presentation deck and recording of the Public Information Centre regarding the proposed parkettes have been added below.


Map of Project Area

Map of Thornbury West project area

Quarterly Progress Reports

 Q2 2022Q1 2022
Project ScopeWithin revised scopeRevised scope
Project ScheduleBehind scheduleOn schedule
Project BudgetWithin budgetWithin budget
NotesStart of construction work has been delayed as utility locates are ongoing.The Town is investigating options for the addition of two Parkettes as a part of the project.

Frequently Asked Questions