Hillside

Notice of Development Activity 
February 2025 - November 2025

Please be advised that construction activities for the Hillside Development will begin on February 24, 2025, and are expected to be completed by November 2025. 

Activities include installing sedimentation/erosion control measures, tree clearing, and installing a channel culvert. This work will be followed by minor earthworks, installing sanitary, water and storm systems, and road construction. 

Additional notice will be provided for any service interruptions or road closures related to construction activities. 

View the Notice of Development Activity

Project Information
Application Type(s)
Subdivision
Town file #
P2750
Address
Part Lot 19, Concession 1
Total Residential Units
20
Project location
Craigleith
Tyrolean Village

Follow This Project

Subscribe now to receive timely updates regarding this project direct to your inbox.

Subscribe

Planning Services Staff received an application to consider a Zoning By-law Amendment on a portion of the subject lands known as Tyrolean Hillside that would increase the maximum permitted height from 2 storeys (8.0 metres) to 2.5 storeys (9.5 metres).  It should be noted that the Tyrolean Hillside project is a Draft Plan Approved subdivision consisting of 20 lots for single detached dwellings originally approved in 1998.

The “Hillside” subdivision was originally draft plan approved and zoned for development in the mid 1990’s.  The subdivision proposes 20 residential lots for single detached dwellings fronting on a new municipal road.  The lots range in size and shape due to the unique topography of the area including a watercourse that flows west to east and the Nippissing Ridge along the easterly boundary of the Draft Plan lands.  In general lots are 18-20 metres frontage and 40 metres deep.


Development Activity - What to Expect

The Town of The Blue Mountains would like to inform those interested in the Hillside Development project that a Pre-Servicing Agreement has been executed, and development activities will commence in February 2025.


Related Documents

Development Timeline

 This icon indicates when the Public Meeting will take place.

 Click or hover over each step for more information.

Visit Explore the Development Process for a more in depth look at each phase.

Pre-Consultation:

  1. completed
  2. completed

Planning:

  1. completed
  2. completed
  3. completed

Development Engineering:Pre-Servicing Agreement in Effect

  1. completed
  2. completed
  3. current step
  4. not completed
  5. not completed

Building:

  1. not completed
  2. not completed
  3. not completed
  4. not completed